Versiunea din 08.04.2016. Text extras automat din fișierul original; aspectul poate diferi. Lipsesc: numerotarea automată. descarcă originalul (.docx, 86 KB)

(Operation Number 44085)

GRANT AGREEMENT

(Moldovan Railways Restructuring Project)

between

REPUBLIC OF MOLDOVA

and

CALEA FERATA DIN MOLDOVA

and

EUROPEAN BANK FOR RECONSTRUCTION AND DEVELOPMENT

in respect of an investment grant

from the EBRD Shareholder Special Fund

Dated 10 november 2015

TABLE OF CONTENTS

ARTICLE I - DEFINITIONS; REFERENCES AND HEADINGS 2

Section 1.01 Definitions 2

Section 1.02 Interpretation 6

ARTICLE II - GRANT FINANCING 6

Section 2.01 Amount, Currency and Purpose 6

Section 2.02 Disbursements 6

Section 2.03 Conditional and Unconditional Reimbursement Commitments 8

Section 2.04 Cancellation by the Recipient 9

Section 2.05 Payment of the Disbursements 9

ARTICLE III - EXECUTION OF THE PROJECT 9

Section 3.01 Cooperation and Information 9

Section 3.02 EMIS Project Implementation 10

Section 3.03 Environmental and Social Compliance 10

Section 3.04 Support Obligations of the Ministry 10

Section 3.05 Project Implementation Unit 11

Section 3.06 Procurement 11

Section 3.07 Project Records and Reports; Examinations 11

ARTICLE IV - FINANCIAL AND OPERATIONAL COVENANTS 13

Section 4.01 Financial Records and Reports 13

Section 4.02 Conduct of Business and Operations 14

Section 4.03 Taxes 14

Section 4.04 Visibility 14

Section 4.05 Fraud and Corruption 14

ARTICLE V - SUSPENSION AND CANCELLATION; REFUND 15

Section 5.01 Suspension 15

Section 5.02 Cancellation by the Bank 16

Section 5.03 Unconditional Reimbursement Commitments Unaffected by Suspension or Cancellation 17

Section 5.04 Obligations of the Recipient and the Ministry 17

Section 5.05 Events of Refund 17

ARTICLE VI - ENFORCEABILITY, GOVERNING LAW, DISPUTE RESOLUTION 18

Section 6.01 Enforceability 18

Section 6.02 Failure to Exercise Rights 18

Section 6.03 Dispute Resolution 18

ARTICLE VII - EFFECTIVENESS; TERMINATION 19

Section 7.01 Effective Date 19

Section 7.02 Conditions Precedent to Effectiveness 19

Section 7.03 Legal Opinions 19

Section 7.04 Termination for Failure to Become Effective 20

Section 7.05 Termination on Performance 20

ARTICLE VIII - MISCELLANEOUS 20

Section 8.01 Notices 20

Section 8.02 Authority to Act 21

Section 8.03 Amendment 21

Section 8.04 English language 21

Section 8.05 Indemnification 22

Section 8.06 Assignments 22

Section 8.07 Rights, Remedies and Waivers 22

Section 8.08 Disclosure 23

Section 8.09 Counterparts 23

SCHEDULE 1 – EMIS PROJECT DESCRIPTION 1

SCHEDULE 2- THE GRANT FINANCED ITEMS 2

EXHIBIT 1 - FORM OF DISBURSEMENT REQUEST 3

EXHIBIT 2 - FORM OF LETTER DESIGNATING AUTHORISED SIGNATORIES 1

GRANT AGREEMENT

This GRANT AGREEMENT (the “Agreement”) is made on 10 November 2015 between Republic of Moldova, represented by the Ministry of Transport and Road Infrastructure (the “Ministry”), Intreprinderea de Stat Calea Ferata din Moldova (hereinafter referred to as the “Recipient”) and the European Bank for Reconstruction and Development (hereinafter referred to as the “Bank” or “EBRD”).

WHEREAS:

  1. EBRD is an international financial institution established under international law pursuant to the Agreement Establishing the European Bank for Reconstruction and Development (the “Agreement Establishing the Bank”) dated 29 May 1990.
  2. The Republic of Moldova and the Recipient have requested assistance in financing part of the Project (as hereinafter defined), which is designed to co-finance the implementation of the EMIS Project (as defined below) constituting integral part of the Project.
  3. On 14 November 2014, the Bank entered into a loan agreement with the Republic of Moldova represented by the Ministry of Finance in its capacity as the Borrower, pursuant to which the Bank as lender agreed to make a loan of EUR 52,500,000 for the financing of part of the Moldovan Railways Restructuring Project (the “Project”), as defined under the Loan Agreement, subject to the terms and conditions set forth in the loan agreement as may be amended from time to time (the “Loan Agreement”).
  4. The proceeds of the Loan Agreement are to be on-lent by the Borrower to the Recipient for the implementation of the Project in accordance with the terms and conditions of a subsidiary loan agreement to be entered into between the Borrower and the Recipient, as may be amended from time to time (the "Subsidiary Loan Agreement").
  5. On 14 November 2014, the Bank entered into a project agreement with the Recipient, as may be amended from time to time (the “Project Agreement”), pursuant to which, in consideration for the Bank entering into the Loan Agreement, the Recipient agreed to carry out the Project in accordance with the terms and conditions of the Project Agreement.
  6. Pursuant to Article 18 of the Agreement Establishing the Bank, the Bank has established the EBRD Shareholder Special Fund (the “Fund”) which is managed and administered in accordance with the Rules of the Fund dated 15 April 2008, as may be amended from time to time (the “Rules of the Fund”).
  7. On 16 June 2009, EBRD Board of Directors approved the Energy Efficiency Management System Programme (the “Programme”) which aims at enhancing competiveness and optimal use of resources through the introduction of best energy management practice in selected Bank`s projects. The Recipient has been selected as a possible beneficiary under the Programme on the basis of the EMIS Project showing high demonstration potential on energy efficiency in accordance with the Programme eligibility criteria.
  8. As part of the project implementation assistance segment of the Project, an independent energy efficiency consultant was contracted by the Bank in 2012, which consultant has identified certain energy saving opportunities in connection with, and beyond the scope of, the Project (the “EMIS Project”) as described in Schedule 1 to this Agreement.
  9. Further to the terms and conditions of the Rules of the Fund, the Bank has agreed to extend, and to manage and administer, for the implementation of the EMIS Project, a grant in an amount not exceeding the lowest of (i) EUR 250,000 or (ii) 50% of the total amount of the Contracts, from the resources of the Fund, subject to and on the terms and conditions set forth in this Agreement.
  10. The remaining 50% of the total amount of the Contracts have been agreed to be financed with the Loan under and subject to the terms and conditions of the Loan Agreement.


NOW, THEREFORE, IT IS HEREBY AGREED AS FOLLOWS:

ARTICLE I - DEFINITIONS; REFERENCES AND HEADINGS

Section 1.01 Definitions

Words and expressions capitalised in this Agreement (including the Exhibits and any Schedules) but not herein defined shall have the same meaning ascribed thereto in the Loan Agreement, the Project Agreement and/or in the Standard Terms and Conditions when used in this Agreement.

Wherever used in this Agreement (including the Appendices and the Recitals), unless the context otherwise requires, the following terms have the following meanings:

“Agreement Establishing

the Bank” has the meaning ascribed to it in Recital A.

“As-Built Documentation” means the “as built” project documentation in respect of the EMIS Project, signed by the relevant Contractors and including “as built” drawings, general schemes, technical description, technical specifications of the EMIS equipment and receipts of all eligible costs incurred in connection with the EMIS Project.

“Commissioning Protocol” means the protocol confirming that the EMIS components have been fully installed in accordance with all applicable laws and regulations, signed by the relevant Contractors and the technical supervisor of the Recipient and certified by the relevant Government Authorities, as applicable.

“Contracts” means the contracts to be entered into between the Recipient and any Contractors, in form and substance satisfactory to the Bank, in connection with the procurement of goods, works and related services for the EMIS Project, including the Grant Financed Items.

“Contractor(s)” means each and all of the contractors and suppliers of good standing and repute to be engaged by the Recipient in connection with the procurement of goods, works and related services for the EMIS Project, including the Grant Financed Items, with each such contractor and Contractor to be selected in accordance with Section 3.06 (Procurement) of this Agreement.

“Disbursement” means the disbursement of any portion of the Grant Financing from time to time pursuant to Section 2.02 (Disbursements) of this Agreement.

“Disbursement Request” has the meaning ascribed to it under Section 2.02 (d) of this Agreement.

“Effective Date” means the date upon which this Agreement becomes effective in accordance with Section 7.01 (Effective Date) of this Agreement.

“EMIS” means the Energy Management Information System.

“EMIS Project” has the meaning ascribed to it in Recital B and as further detailed in Schedule 1 to this Agreement.

“EMIS Project Completion

Date” means the date on which all of the following have occurred:

the Recipient shall have delivered to the Bank and to the Project Implementation Consultant, if applicable, in form and substance satisfactory to the Bank, signed by the Recipient`s Authorized Representative, a notice certifying that EMIS Project has been completed together with the EMIS Project Completion Documentation, accompanied by translations in the English language, if the originals are executed in another language;

the Bank shall have received from the Project Implementation Consultant, if applicable, in form and substance satisfactory to the Bank, a notice confirming that the EMIS Project has been completed; and

the Bank shall have delivered to the Recipient a notice confirming that the EMIS Project has been completed.

“EMIS Project Completion

Documentation” means the As-Build Documentation, Commissioning Protocol and Start-Up Test Protocol collectively.

“Fund” has the meaning ascribed to it in Recital F.

“Grant Financed Items” means the goods, works and related services required for the implementation of the EMIS Project and to be financed by the Grant Financing as further described in Schedule 2 to this Agreement.

“Grant Financing” has the meaning ascribed to it under Section 2.01(a) (Amount, Currency and Purpose) of this Agreement.

“Last Availability Date of

Grant Financing” means the date specified in Section 2.02(a) (Last Availability Date of Grant Financing) of this Agreement.

“Loan Agreement” has the meaning ascribed to it in Recital C.

“Loan Financing” means financing made or to be made available by the Bank to the Borrower in its capacity as the Borrower under the Loan Agreement and on-lent to the Recipient pursuant to the terms of the Subsidiary Loan Agreement.

“Ministry” means Republic of Moldova, as represented by the Ministry of Transport and Road Infrastructure or any other relevant ministry.

“Ministry’s Authorised

Representative” means the Minister of Transport and Road Infrastructure.

“Programme ” has the meaning ascribed to it in Recital G.

“Project” has the meaning ascribed to it in Recital C.

“Project Agreement” has the meaning ascribed to it in Recital E.

“Project Implementation

Consultant” means the consultant(s) engaged or caused to be engaged by the Recipient in accordance with Section 2.06 (Consultants) of the Project Agreement to assist with the implementation of the Project.

“Recipient” means Calea Ferata din Moldova.

“Recipient’s Authorised

Representative” means the General Director, or any other person duly authorised to act on behalf and to represent the Recipient.

“Reimbursement

Commitment” means a commitment referred to in Section 2.03 (Conditional and Unconditional Reimbursement Commitments) of this Agreement, and may be a “conditional Reimbursement Commitment” or an “unconditional Reimbursement Commitment”, as those terms are used in that Section.

“Rules of the Fund” has the meaning ascribed to it in Recital F.

“Standard Terms and

Conditions” means the Standard Terms and Conditions of EBRD dated 1 December 2012.

“Start-Up Test Protocol” means the protocol signed by the Contractor who has performed the installation of the EMIS, and confirming that the EMIS have passed all required start-up tests and is operational.

“Subsidiary Loan

Agreement” has the meaning ascribed to it in Recital D.

Section 1.02 Interpretation

In this Agreement:

(d) reference to a specified Article, Section, Schedule or Exhibit shall, except where stated otherwise in this Agreement, be construed as a reference to that specified Article or Section of, or Appendix or Exhibit to, this Agreement.

ARTICLE II - GRANT FINANCING

Section 2.01 Amount, Currency and Purpose

Section 2.02 Disbursements

Subject to Section 5.01 (Suspension), Section 5.02 (Cancellation by the Bank) and Section 7.02 (Conditions Precedent to Effectiveness) of this Agreement, the Grant Financing shall be disbursed by the Bank in one or more Disbursement(s), subject to the following provisions:

The Recipient’s right to request a Disbursement in accordance with this Agreement shall become effective on the Effective Date and shall terminate 4 (four) months from the EMIS Project Completion Date or such later date that the Bank may in its discretion establish and notify to the Recipient.

Except as the Bank otherwise agrees, Disbursements under this Agreement shall only be made to finance:

Without limiting the generality of this Section 2.02, any Disbursement under this Agreement in respect of one or more Grant Financed Items shall be subject to the fulfilment, or, at the sole discretion of the Bank, the waiver, whether in whole or in part, on the date of Disbursement Request:

Disbursements shall be made in EUR in an amount equivalent to the expenditures to be financed out of the proceeds of the Grant Financing. In the case of expenditures incurred in a currency or currencies other than EUR, the equivalent Disbursement amount shall be determined as follows:

In exceptional circumstances, the Bank may grant a request by the Recipient that payment be made in a currency or currencies other than EUR or the currency of expenditures. In that case, the Bank will purchase such currency or currencies in such manner as the Bank may deem appropriate. The equivalent Disbursement amount shall be determined by the Bank on the basis of the exchange costs that were or would have been incurred by the Bank in using EUR to meet the request.

Except for the last Disbursement or except as the Bank otherwise agrees, Disbursements shall be made in amounts of not less than the amount of the grant as per Section 2.01 (a).

Section 2.03 Conditional and Unconditional Reimbursement Commitments

Section 2.04 Cancellation by the Recipient

The Recipient may cancel at any time, on not less than thirty (30) Business Days prior written notice to the Bank, in whole or in part, any undisbursed portion of the Grant Financing. Any such notice of cancellation by the Recipient shall be irrevocable and binding on the Recipient.

Section 2.05 Payment of the Disbursements

ARTICLE III - EXECUTION OF THE PROJECT

Section 3.01 Cooperation and Information

  1. references to the “Borrower” were read as references to the “Recipient”;
  2. references to the “Guarantor” were read as references to the “Ministry”;
  3. references to the “Loan” were read as references to the “Grant Financing”;
  4. references to the “the Loan Agreement” were read as references to “this Agreement”; and
      1. In receiving information pursuant to the Loan Agreement and the Project Agreement, the Bank may use and rely on any such information in its capacity as provider of the Grant Financing under this Agreement.

Section 3.02 EMIS Project Implementation

  1. references to the “Borrower” were read as references to the “Recipient”; and
  2. references to the “proceeds of the Loan” were read as references to the “Grant Financing”.

Section 3.03 Environmental and Social Compliance

Except as the Bank otherwise agrees, the Recipient shall ensure that the EMIS Project is carried out in accordance with Section 2.05(Environmental and Social Compliance Covenants) of the Project Agreement.

Section 3.04 Support Obligations of the Ministry

Section 3.05 Project Implementation Unit

The Recipient shall ensure that the activities and responsibilities of the PIU, referred to in Section 2.03 (Project Implementation Unit) of the Project Agreement, include the procurement of goods, works and related services for the EMIS Project, (including the Grant Financed Items) and implementation of the EMIS Project as a whole.

Section 3.06 Procurement

Except as the Bank otherwise agrees, the procurement of all goods, works and related services required for the EMIS Project, including all Grant Financed Items, shall be governed by the EBRD PPR, and the following shall apply:

Section 3.07 Project Records and Reports; Examinations

  1. The Recipient shall ensure that information furnished to the Bank by the Recipient and records maintained by the Recipient, are in compliance with the Recipient’s obligations, in its capacity as the Project Entity, pursuant to Section 2.07 (Reporting Frequency and Submission Requirements) of the Project Agreement as well as Section 4.04 (Project Records and Reports) and Section 5.02 (Reporting) of the Standard Terms and Conditions:
        1. includes detailed information concerning the Contracts, the Contractors, Disbursements, the Grant Financing and its use, the Grant Financed Items, as well as the status of compliance with each of the covenants contained in this Agreement in form and substance satisfactory to the Bank;
        2. contains sufficient information to enable tracking of the Grant Financing distinct from the Loan Financing; and
        3. includes such other information regarding inter alia the Recipient, the EMIS Project and the transactions contemplated under this Agreement as the Bank may from time to time reasonably request.
  2. As soon as available but in any event, within thirty (30) days after completion of the last Contract, the Recipient shall furnish to the Bank, certified by an authorised officer of the Recipient, a final report with regard to the use of the Grant Financing, which will specify in detail all Contracts, all Contractors, the Grant Financed Items and the delivery and erection schedules, and comparison against original forecasts.
  3. As soon as available but in any event, within thirty (30) days after the EMIS Project Completion Date, the Recipient shall furnish to the Bank, certified by an authorised officer of the Recipient, a final report with regard to the EMIS Project, identifying the use of the Grant Financing.
  4. The Recipient shall enable the Bank, and its representatives, at the Bank’s request:
        1. to visit any facilities and construction sites relating to the EMIS Project;
        2. to examine any and all goods, works and services financed out of the proceeds of the Grant Financing and the Loan in relation to the EMIS Project and any plants, installations, sites, works, buildings, property, equipment, records and documents relevant to the performance of the obligations of the Recipient under this Agreement; and
        3. for these purposes, to meet and hold discussions with such representatives and employees of the Recipient as the Bank may deem necessary and appropriate.
  5. Upon the award of any Contract, the Bank may publish a description thereof, the name and nationality of the Contractor and the contract price.
  6. The Recipient shall ensure that the Bank, and its representatives are provided access to the Recipient’s books of account and records related to the EMIS Project.
  7. Immediately upon the occurrence of any Event of Refund as provided for in Section 5.05 of this Agreement, the Recipient shall give the Bank notice thereof by facsimile transmission specifying the nature of such Event of Refund and any steps the Recipient is taking to remedy the same.

ARTICLE IV - FINANCIAL AND OPERATIONAL COVENANTS

Financial Records and Reports

  1. The Recipient shall maintain separate records and accounts in respect of the Grant Financing, in accordance with internationally accepted accounting standards acceptable to the Bank consistently applied;
  2. The Recipient shall ensure that the information furnished to the Bank by the Recipient and records maintained by the Recipient, are in compliance with the Recipient’s obligations, in its capacity as the Project Entity, pursuant to Section 3.01 (Financial Records and Reports) of the Project Agreement as well as Section 5.02(c)(i) (Reporting) of the Standard Terms and Conditions:
        1. includes detailed information concerning the Grant Financing and its use, in form and substance satisfactory to the Bank;
        2. contains sufficient information to enable tracking of the Grant Financing distinct from the Loan Financing; and
        3. includes such other information concerning such records, accounts and financial statements as the Bank may from time to time reasonably request.
  3. The Recipient shall ensure that the authorisation given to the Auditors pursuant to Section 3.04 (j) of the Project Agreement to communicate directly with the Bank extends to information requested by the Bank under the terms of this Agreement and in connection with the use of the Grant Financing.

Conduct of Business and Operations

The Recipient shall except as the Bank otherwise agrees:

  1. duly perform all of its obligations under this Agreement and in its capacity as Project Entity, under the Project Agreement;
  2. not make changes or permit changes to be made to its Statutes if such changes are inconsistent with any provision of this Agreement except for the amendments carried out in the context of the implementation of the Restructuring Action Plan (which has been approved by the Bank in writing); and
  3. execute any other documents and take any other actions that the Bank determines are necessary or desirable to give effect to this Agreement.

Taxes

  1. The Recipient shall pay, when due, all Taxes levied on it and payable on, or in connection with, the execution, issue, delivery, registration or notarisation of this Agreement (including the provision of the Grant Financing) or any other document related to this Agreement. The Recipient shall make timely filings of all Tax returns and governmental reports required to be filed or submitted under any applicable law;
  2. No part of the proceeds of the Grant Financing shall be used, directly or indirectly, for the payment of any Taxes, be they direct or indirect, in the territory of the Republic of Moldova or elsewhere.

Visibility

The Recipient shall take appropriate measures to publicise in relevant publications, communications, as well as media, the fact that the EMIS Project has received funding from inter alia the Fund.

Fraud and Corruption

The Recipient shall not, and shall not authorise or permit any of its officers, directors, authorised employees, agents or representatives to, engage in with respect to the EMIS Project, the Grant Financing or any transactions contemplated by this Agreement, any Prohibited Practice.

ARTICLE V - SUSPENSION AND CANCELLATION; REFUND

Suspension

  1. If any of the following events shall have occurred and be continuing, the Bank may, by notice to the Recipient and the Ministry, suspend in whole or in part, the right of the Recipient to any further Disbursement under this Agreement:
        1. any of the Loan Agreement, or the Project Agreement, or the Subsidiary Loan Agreement, ceases to be in full force and effect or is terminated;
        2. the Recipient has failed or fails to perform any of its obligations under this Agreement, or, in its capacity as the Project Entity under the Project Agreement, or, in its capacity as a borrower under the Subsidiary Loan Agreement.
        3. the Ministry, in its capacity as the Borrower under the Loan Agreement, has failed or fails to perform any of its obligations under this Agreement or under the Loan Agreement, or, in its capacity as a lender under the Subsidiary Loan Agreement;
        4. the Bank has suspended or cancelled, or an event has occurred which gives the Bank the right to suspend or cancel, in whole or in part, the right of the Borrower to make applications for Drawdowns, under the Loan Agreement pursuant to Section 7.01 (Suspension) and Section 7.02 (Cancellation by the Bank) of the Standard Terms and Conditions;
        5. any event specified in Section 7.06 (Events of Acceleration) of the Standard Terms and Conditions has occurred or is continuing and the Bank has declared all or any portion of the Loan Financing to be due and payable pursuant to Section 7.06 (Events of Acceleration) of the Standard Terms and Conditions;
        6. an extraordinary situation has arisen as a result of events which have occurred which shall make it improbable the EMIS Project can be carried out or the Recipient or the Ministry will be able to perform their obligations under this Agreement;
        7. a representation or warranty made by the Recipient or the Ministry in connection with this Agreement shall have been incorrect or misleading in any material respect;
        8. except as permitted under Section IV(b) of the Loan Agreement, the Statutes of the Recipient shall have been amended, suspended, abrogated, repealed or waived in such a way as to affect materially and adversely the operations or the financial condition of the Recipient or its ability to carry out the EMIS Project or to perform any of its obligations under this Agreement;
        9. the Ministry in its capacity as the Borrower under the Loan Agreement has cancelled in whole or in part any undisbursed portion of the Loan Financing pursuant to Section 3.08 (Cancellation) of the Standard Terms and Conditions;
        10. the Fund has terminated pursuant to the Rules of the Fund; or
        11. the Recipient, the Ministry, a Contractor, or any of their officers, employees, agents or representatives has been found by a judicial process or other official enquiry to have engaged in any Prohibited Practice with respect to the EMIS Project, the Grant Financing or any transactions contemplated by this Agreement.
  2. The right of the Recipient to any further Disbursement shall continue to be suspended in whole or in part, as the case may be, until the event or events which gave rise to suspension shall have ceased to exist, unless the Bank shall have notified the Recipient and the Ministry that the right to further Disbursements has been restored; provided, however that, that the right to further Disbursements shall be restored only to the extent and subject to the conditions specified in such notice, and no such notice shall affect or impair any right, power or remedy of the Bank in respect of any other subsequent event described in this Section.

Cancellation by the Bank

  1. If at any time the Bank determines, after consultation with the Recipient and the Ministry, that an amount of the Grant Financing will not be required to finance costs of the EMIS Project to be financed out of the Grant Financing, the Bank may, by notice to the Recipient and the Ministry, cancel such amount of the Grant Financing. On the Last Availability Date of the Grant Financing, any undisbursed portion of the Grant Financing shall be cancelled automatically, except as the Bank otherwise agrees.
  2. If the right of the Recipient to Disbursement of any portion of the Grant Financing under this Agreement shall have been suspended pursuant to Section 5.01 (Suspension) of this Agreement for a continuous period of thirty (30) days, the Bank may, by notice to the Recipient and the Ministry, cancel the Grant Financing, in whole or in part.
  3. If the Bank has cancelled, or an event has occurred which gives the Bank the right to cancel, in whole or in part, the Loan Financing pursuant to Section 7.02 (Cancellation by the Bank) of the Standard Terms and Conditions, the Bank may, by notice to the Recipient and the Ministry, cancel the Grant Financing, in whole or in part.
  4. If at any time, the Bank determines that :
        1. the procurement of any of the Grant Financed Items is inconsistent with this Agreement;
        2. funds disbursed under this Agreement have been used for purposes other than those provided for under this Agreement; or
        3. with respect to any Contract, any representative of the Recipient, the Ministry, or any Contractor has engaged in any Prohibited Practice during the procurement or execution of such Contract, without the Recipient and the Ministry having taken timely and appropriate action satisfactory to the Bank to remedy the situation;

the Bank may, by notice to the Recipient and the Ministry, cancel the Grant Financing in whole or in part. Such cancellation shall take effect when notice is given.

  1. If at any time the Bank determines that any representative of the Recipient or the Ministry, or any Contractor has been found by a judicial process or other official enquiry to have engaged in any Prohibited Practice with respect to the Project, the Grant Financing or any transactions contemplated by this Agreement, the Bank may, by notice to the Recipient and the Ministry, cancel the Grant Financing in whole or in part. Such cancellation shall take effect when notice is given.

Unconditional Reimbursement Commitments Unaffected by Suspension or Cancellation

No cancellation or suspension shall apply to amounts subject to an unconditional Reimbursement Commitment entered into by the Bank pursuant to Section 2.03 (Conditional and Unconditional Reimbursement Commitments) of this Agreement except as expressly provided in such commitment.

Obligations of the Recipient and the Ministry

Notwithstanding any cancellation or suspension, all the provisions of this Agreement shall continue in full force and effect, except as specifically provided herein.

Events of Refund

If any of the following events shall have occurred and shall be continuing for the period specified below, then at any time during the continuance of that event the Bank may, by notice to the Recipient and the Ministry, demand that the Recipient and/or the Ministry refund all or any portion of the Grant Financing (and pay any other amounts payable under this Agreement) and the same shall thereupon become (anything in this Agreement to the contrary notwithstanding), due and payable immediately:

  1. Any event specified in Section 5.01(a)(1) (Suspension) of this Agreement has occurred.
  2. Any event specified in Section 5.01(a)(2) or 5.01(a)(3), (Suspension) of this Agreement has occurred and, if capable of remedy, has continued for a period of thirty (30) days after notice thereof has been given by the Bank.
  3. Any Event of Acceleration specified in the Loan Agreement and the Standard Terms and Conditions has occurred or is continuing and the Bank has declared all or any portion of the Loan Financing to be due and payable pursuant to Section 7.06 (Events of Acceleration) of the Standard Terms and Conditions.
  4. At any time the Bank determines that any representative of the Recipient, the Ministry, or any Contractor has been found by a judicial process or other official enquiry to have engaged in any Prohibited Practice with respect to the Project, the Grant Financing or any transactions contemplated by this Agreement,
  5. The Recipient in its capacity as the Borrower under the Loan Agreement has cancelled in whole or in part any undisbursed portion of the Loan Financing pursuant to Section 3.08 (Cancellation) of the Standard Terms and Conditions.

ARTICLE VI - ENFORCEABILITY, GOVERNING LAW, DISPUTE RESOLUTION

Enforceability

The rights and obligations of the Recipient and the Ministry shall be valid and enforceable in accordance with their terms, notwithstanding any law of the Republic of Moldova to the contrary. The Recipient and the Ministry shall not be entitled under any circumstances to assert any claim that any provision of this Agreement is invalid or unenforceable for any reason.

Failure to Exercise Rights

No delay in exercising, or omission to exercise, any right, power or remedy, accruing to either party under this Agreement upon any default shall impair any such right, power or remedy or be construed to be a waiver thereof or an acquiescence in such default; nor shall the action of such party in respect of any default, or any acquiescence in any default, affect or impair any right, power or remedy of such party in respect of any other subsequent default.

Dispute Resolution

The provisions of Section 8.04 (Dispute Resolution) of the Standard Terms and Conditions shall apply as if set out herein in full mutatis mutandis including, without prejudice to the generality thereof, as if:

  1. references to “the Loan Agreement” or “the Project Agreement” were read as references to “this Agreement”;
  2. references to “the Borrower”, or “any Project Entity” were read as references to “the Recipient”; and
  3. references to “the Guarantor” were read as references to “the Ministry”.

ARTICLE VII - EFFECTIVENESS; TERMINATION

Effective Date

Except as the Bank and the Recipient and the Ministry shall otherwise agree, this Agreement shall become effective on the date upon which the Bank dispatches to the Recipient and the Ministry notice of the Bank’s acceptance of the evidence required by Section 7.02 (Conditions Precedent to Effectiveness) and Section 7.03 (Legal Opinions) of this Agreement.

Conditions Precedent to Effectiveness

This Agreement shall not become effective unless the Bank is satisfied that no event referred to in Section 5.01(a) (Suspension) or Section 5.05 (Events of Refund) of this Agreement has occurred and is continuing; and until the following conditions precedent have been fulfilled, in form and substance satisfactory to the Bank, or at the sole discretion of the Bank waived, whether in whole or in part and whether subject to conditions or unconditionally:

  1. the Bank shall have received two duly executed originals of this Agreement;
  2. all conditions precedents of the effectiveness of Tranche 1 under Section 5.01(a) (Condition Precedents to the Effectiveness of Tranche 1) of the Loan Agreement, except for effectiveness of this Agreement, shall have been fulfilled in form and substance satisfactory to the Bank or waived by the Bank in accordance with the terms of the Loan Agreement.
  3. the Bank shall have received evidence, in form and substance satisfactory to the Bank, that the execution and delivery of this Agreement on behalf of the Recipient and the Ministry have been duly authorised or ratified by all necessary governmental, administrative and corporate actions;
  4. the Bank has been provided with such other documents it may have reasonably requested.

Legal Opinions

As part of the evidence to be furnished pursuant to Section 7.02 (Conditions Precedent to Effectiveness) of this Agreement, the Minister of Justice of the Republic of Moldova shall furnish, or cause to be furnished, to the Bank an opinion, on behalf of the Recipient and the Ministry in form and substance satisfactory to the Bank, in respect of this Agreement, and showing that this Agreement has been duly authorised or ratified by, and executed and delivered on behalf of the Recipient and the Ministry, and constitutes a valid and legally binding obligation of the Recipient and the Ministry, enforceable in accordance with its terms.

Termination for Failure to Become Effective

  1. If the Loan Agreement is not effective by the date specified in Section 5.03 (Termination for Failure to Become Effective) of the Loan Agreement or any further date notified by the Bank to the Recipient in its capacity as the Borrower pursuant to Section 9.04 (Termination for Failure to Become Effective) of the Standard Terms and Conditions, all obligations of the Bank under this Agreement shall terminate unless the Bank, after consideration of the reasons for the delay, shall establish a later date for the purposes of this Section. The Bank shall promptly notify the Recipient and the Ministry of such later date.

Termination on Performance

  1. This Agreement shall continue in force until the Recipient and the Ministry have performed all of their respective obligations in accordance with the provisions hereof, unless earlier terminated in accordance with its terms; provided that Section 6.03 (Dispute Resolution) shall survive the termination of this Agreement.
  2. Notwithstanding anything to the contrary in this Agreement, the provisions of Section 5.05(d) (Events of Refund) shall survive the termination of this Agreement for five (5) years after the Project Completion Date.

ARTICLE VIII - MISCELLANEOUS

Notices

Any notice or request required or permitted to be given or made under this Agreement shall be in writing. Except as otherwise provided in Section 7.01 (Effective Date) of this Agreement, such notice or request shall be deemed to have been duly given or made when it has been delivered to the party to which it is required to be given or made at the party’s address specified below or at such other address as such party shall have specified in writing to the other party giving the notice or making the request. Except as otherwise provided in this Agreement or the EBRD Disbursement Handbook, such delivery may be made by hand, mail or facsimile transmission. Deliveries made by facsimile transmission shall also be confirmed by mail.

For the Recipient:

Calea Ferata din Moldova

48 Vlaicu Pircalab Street

Chisinau MD-2012

Republic of Moldova

Attention: General Director

Fax: +373 22 22 13 80

For the Ministry:

Republic of Moldova

Ministry of Transport and Road Infrastructure

162 Ștefan cel Mare și Sfînt bvd.

Chisinau, MD 2004

Moldova

Attention: Minister of Transport and Road Infrastructure

Fax: +373 22 22 5393

For the Bank:

European Bank for Reconstruction and Development

One Exchange Square

London EC2A 2JN

United Kingdom

Attention: Operation Administration Department

Fax: +44 20 7338 6100

Authority to Act

Any action required or permitted to be taken and any documents required or permitted to be executed under this Agreement by the Recipient or the Ministry, shall be taken or executed by the Authorised Representatives of the Recipient and the Ministry, as the case may be, or such other officers of the Recipient and the Ministry as any such Authorised Representatives shall designate in writing. The Recipient and the Ministry shall furnish to the Bank evidence of the authority and the authorised specimen signature of such officer substantially in the form of Exhibit 2 (Form of Letter Designating Authorised Signatories).

Amendment

This Agreement may be amended by a written instrument signed by the Recipient’s Authorised Representative, the Ministry’s Authorised Representative and by a duly authorised officer of the Bank.

English language

This Agreement has been prepared and executed in English. Any document delivered pursuant to this Agreement shall be in the English language. Documents in any other language shall be accompanied by an English translation thereof certified as being an approved translation and such approved translation shall be conclusive and shall be the governing version.

Indemnification

  1. The Ministry and the Recipient assume full liability for, and agree to and shall indemnify and hold harmless the Bank and its officers, directors, employees, agents and servants against and from, any and all liabilities, obligations, losses, damages (compensatory, punitive or otherwise), penalties, claims, actions, Taxes, suits, costs and expenses (including, reasonable legal counsel's fees and expenses and costs of investigation) of whatsoever kind and nature, including, without prejudice to the generality of the foregoing, those arising in contract or tort (including negligence) or by strict liability or otherwise, which are imposed on, incurred by or asserted against the Bank or any of its officers, directors, employees, agents or servants (whether or not also indemnified by any other person under any other document) and which in any way relate to or arise out of, whether directly or indirectly:
        1. any of the transactions contemplated by this Agreement or the execution, delivery or performance thereof;
        2. the operation or maintenance of the Recipient’s facilities or the ownership, control or possession thereof by the Recipient; or
        3. the exercise by the Bank of any of its rights and remedies under this Agreement; and

provided that the Bank shall not have any right to be indemnified hereunder for its own gross negligence or wilful misconduct.

  1. The Recipient and the Ministry acknowledge that the Bank is entering into this Agreement, and has acted, solely as a grant provider, and not as an advisor, to the Recipient and the Ministry. The Recipient and the Ministry represent and warrant that, in entering into this Agreement, they have engaged, and relied upon advice given to them by, their own legal, financial and other professional advisors and they have not relied on and will not hereafter rely on any advice given to them by the Bank.

Assignments

The Recipient and the Ministry may not assign or otherwise transfer all or any part of their respective rights or obligations under this Agreement without the prior written consent of the Bank.

Rights, Remedies and Waivers

The rights and remedies of the Bank under this Agreement shall not be prejudiced by any act or thing which might, apart from this Section, prejudice such rights or remedies. No course of dealing and no delay in exercising, or failure to exercise, any right, power or remedy of the Bank shall impair any such right, power or remedy or be construed to be a waiver thereof. Any waiver of any of the terms or conditions of this Agreement shall be in writing and signed by the Bank. In the event that the Bank waives a condition to any Disbursement of the Grant Financing, the Recipient shall, by receiving such Disbursement, be deemed to have agreed to the terms of such waiver and the right of the Bank to require compliance with such condition shall be expressly preserved for the purposes of any subsequent Disbursement. The rights and remedies provided in this Agreement and the other agreements contemplated hereby are cumulative and shall not preclude any other or further exercise thereof or the exercise of any other right or remedy.

Disclosure

The Bank may disclose such documents, information and records regarding the Recipient and this transaction (including copies of this Agreement and any other agreement contemplated hereby) as the Bank deems appropriate for any purposes in connection with any dispute involving the Recipient and/or the Ministry, for the purpose of preserving or enforcing any of the Bank’s rights under this Agreement or any other agreement contemplated hereby or collecting any amount owing to the Bank for the purpose of reporting pursuant to the Rules of the Fund.

Counterparts

This Agreement may be executed in any number of counterparts, each of which shall be deemed an original, but all of which together shall constitute one and the same agreement.

IN WITNESS WHEREOF, the parties hereto, acting their duly authorised representatives, have caused this Agreement to be signed in six copies as of the date first above written.

CALEA FERATA DIN MOLDOVA

By: ______________________

Name:

Title:

REPUBLIC OF MOLDOVA

By: ______________________

Name:

Title:

EUROPEAN BANK FOR RECONSTRUCTION AND DEVELOPMENT

By: ______________________

Name:

Title:

SCHEDULE 1 – EMIS PROJECT DESCRIPTION

The EMIS is fundamental for the creation and application of any energy efficiency measures in the railway system. In fact, the system is not an energy saving measure as such but should rather be considered as a key enabler for the implementation of any other measures: from the knowledge of the current energy profile, new practices, strategies, short or even long term measures may take place, from energy efficient timetabling, real time command to the train drivers for peak shaving, support incentive schemes based on energy use measurement, modernisation of fixed installations, etc.

The EMIS will be a dashboard for the managers in the Recipient, enabling them in understanding the behaviour of the whole system, properly characterising the energy profile of each user or group of users in the railway environment.

It is recommended to adopt a scalable approach: at a first phase, the system will include meters in 92 buildings (81 stations, 7 workshops and other administrative buildings) and 15 fuel storage depots meters together with the central workstation, server and dashboard, representing the basis on which a later expansion with on board meters can be implemented. Overall eligible costs are assessed up to EUR 500,000, including the necessary training on the new system and their applications. Further indicative details are provided in Table 1 of this appendix. The second phase, not covered under this Grant Financing, will later incorporate on-board meters in diesel vehicles.

According to the analysis which has been done by an independent consultant, implementation of driving and corporate strategies resulting from the better understanding of the energy costs will allow the company to reduce its energy bill in 5 per cent of electricity costs and 1.5 per cent of traction diesel costs in the first phase. Considering the energy bill for an average month, potential for energy savings can be estimated to be up to 20,000 GJ/yr, which would reduce 1,500 tonnes of GHG emissions and more than EUR 500,000 per year. Therefore, the implementation of the EMIS is a key tool to successfully reduce energy consumption and face the restructuring requirements and is fundamental for the creation and application of any energy efficiency measures in the railway system.

SCHEDULE 2 – THE GRANT FINANCED ITEMS

The table shown in this Schedule sets forth the Grant Financed Items, the indicative cost of the Conception, Design and Implementation of EMIS Project and amount of the Grant Financing allocated to each Grant Financed Item.

Nr.

Item

Indicative cost (EUR)

1

License

60,000

2

Hardware (mid-sized server) and work stations

30,000

3

Engineering: design specification, supplier selection and supervision

150,000

4

System Engineering: project integration and commissioning

150,000

5

Building Meters

25,000

6

Fuel storage depots meters

40,000

7

Training

45,000

Total

500,000

Grant Financing

250,000

EBRD loan

250,000

Source: Energy Audit (D’Appolonia, 2012)

EXHIBIT 1 – FORM OF DISBURSEMENT REQUEST

[To Be Typed on Letterhead of the Recipient]

[Date]

European Bank for Reconstruction and Development

One Exchange Square

London EC2A 2JN

United Kingdom

Attention Operation Administration Department

Operation No. [ ] (Grant Component)

Disbursement Request No. [1]

Re: Grant Agreement dated _____ between the [Recipient], [Sovereign] and the European Bank for Reconstruction and Development (the “Bank”).

We hereby request the following Disbursement in accordance with the provisions of the above mentioned Grant Agreement:

Grant Currency: [EUR]

Currency of payment required: [2]

Financed Amount(s) / currency: [3]

Value Date: [4]

Payable to (Payee): [5]

Payment Instructions (Payee’s Banking Details):

Payee’s Account Name: [6]

Payee’s Account Number: [7]

Payee’s Bank Name: [8]

Payee’s Bank Address: [9]

Payee’s Bank’s Correspondent details:

Correspondent Bank Name: [10]

Address: [11]

Account Name: [12]

Account Number: [13]

Payment Reference: [14]

We hereby certify that we have not previously requested disbursement from the Grant Financing to meet these expenditures. We have not obtained and do not intend to obtain funds for this purpose out of the proceeds of any other grant, credit or loan.

The goods and services covered by this request have been or are being purchased in accordance with the terms of the Grant Agreement.

We hereby confirm to the EBRD that (i) we are in compliance with our obligations as set out in the Grant Agreement and the Loan Agreement and (ii) that no event has occurred which is liable to affect materially and adversely our operations or financial condition or our ability to carry out the Project or to perform any of our obligations under the Grant Agreement.

Yours faithfully,

By: ______________________________

Name:

Title:

Enclosures: - Total number of Summary Sheets: [16]

- Total number of document items: [17]

Notes for completion of the form of Disbursement Request

[1] The Recipient should number each request form. The first request for a grant disbursement will be number 1, the following requests will be numbers 2, 3, etc. It is up to the recipient to keep track of the number of all grant disbursement requests that it has made under the given Grant Agreement. The request forms should follow the same sequential numbering system, whether they are for a direct payment disbursement, or for the issue of a reimbursement commitment. The use of this numbering system avoids confusion in case forms are held up in the post, are faxed more than once, etc.

[2] Please state currency of actual payment required. This will be either the grant currency, or the currency of the expenditures (see [3] below). Alternatively, in some circumstances the Bank may agree to pay in a third currency, in which case it would act as the recipient’s agent in order to obtain this currency.

If payment is required in more than one currency, then a different application form should be used per currency.

[3] The financed amount(s) are the original expenditures, in their original currency as detailed on the summary sheet, calculated at the appropriate percentage specified in the Grant Agreement for the applicable eligible Grant Financed Item. The amount(s) given here should correspond with the total amount(s) in section [15] of the summary sheet.

[4] The value date is the date that the EBRD's account is debited with the payment amount of the disbursement. The EBRD cannot guarantee that the payee's account will be credited on the same date, as this depends on the procedures adopted by the clearing system or the recipient bank in the country of the payee. There should be 15 business days minimum between the date that the EBRD receives the application and the requested value date. If in fact the payment is needed as soon as possible, instead of on that specific value date, it may be better not to give a specific date, but to put "as soon as possible" in this field [4]. In that case the EBRD will make the payment in any case within 15 business days, but earlier if possible. (Please note payment can only be guaranteed within 15 business days if the disbursement request is correct and complete.)

[5] The Disbursement is paid out to the payee. Normally the payee will be the Contractor, but provided that the Bank has agreed otherwise in writing and the enclosed documentation (see the summary sheet) provides evidence that the borrower has already paid the Contractor, then payment may be made to the Recipient.

[6] The payee's account name in most cases will simply be the name of the payee.

[7] The payee's account number is required to avoid delays. In a growing number of countries, banks will refuse to make payment if the payee's account number is not given in the payment instructions.

[8] The payee's bank is the bank where the payee's account is held. Please indicate bank name and town.

[9] Instead of the address, the sorting code or SWIFT code can be given.

[10] The correspondent bank of the payee's bank is only required if payment is not to be made in the currency of the country where the payee's bank is located. In that case, the correspondent bank is the bank, located in the country of the payment currency, with which the payee's bank holds an account.

[11] Instead of an address, the sort code or SWIFT code of the correspondent bank can be given.

[12] The payee's bank's account name in most cases will simply be the name of the payee's bank.

[13] The payee's bank's account number is essential if the payee bank holds more than one account with the correspondent bank, or if it is not a member of SWIFT (the international electronic payment settlement system). Otherwise this number is useful but not mandatory. Where applicable the IBAN No. (International Bank Account Number) should be quoted.

[14] The payment reference which the EBRD will send with the payment helps the payee to identify the payment. If no specific reference is requested, the EBRD will mention the Recipient’s name and the agreement number.

[15] Signature. The request summary sheet should be signed off by or on behalf of the Recipient.

[16] The summary sheets list all the items of documentation enclosed to support the Disbursement Request application. If there are many items, it is advisable to use a separate summary sheet per category.

[17] The documentation items (contracts, invoices, receipts, etc.) are to be numbered and presented in the same order as they appear on the summary sheets. Their total number should be indicated here to facilitate the EBRD's review.

EUROPEAN BANK FOR RECONSTRUCTION AND DEVELOPMENT

Recipient Name: [1]

........................

Operation

No : [3]................

Request

No: [4] .................

Disbursement

(ref.no./ name/ %)

Date: [2]

........................

Summary Sheet No : [5]

.....................

Grant Financed Item: [6]

.........../................../.....

Name and

Brief Description

Currency

Currency &

Amount of

Item

Description

Contract

Address of

of Goods , Works

and Total

Amount of

Financing in currency

No

of Item

No. and Date

Contractor

or Services

Amount of

Eligible

of expenditure

Contract

Expenditure

[7]

[8]

[9]

[10]

[11]

[12]

[13]

[14]

Signature

TOTAL (per currency)

[15]

[16]..............................

Notes for completion of Disbursement Request Summary Sheet

[1] Name. Recipient’s name. This should be the same as on the Disbursement Request form to which this summary sheet belongs.

[2] Date. Date of request. This should be the same as on the Disbursement Request form to which this summary sheet belongs.

[3] Operation number. This number is the same as on the Disbursement Request form to which this summary sheet belongs.

[4] Request number. This is the number of the Disbursement Request form to which this summary sheet belongs.

[5] Summary sheet number. For each Disbursement Request, the summary sheets should be numbered starting from 1, and their total number noted on the Disbursement Request form to which they belong.

[6] Disbursement Grant Financed Item. This is the Grant Financed Item for the project, to be financed out of the proceeds of the requested Disbursement. Please consult the Grant Agreement to find the name and reference number of the Grant Financed Item, and the percentage of expenditures to be financed (for example, "Grant Financed Item no. (3) , equipment, 60%").

If one Disbursement Request covers expenditures from more than one Grant Financed Item, then a separate summary sheet is to be used for each Grant Financed Item.

[7] Item number. All document items (invoices, contracts, receipts, etc.) should be presented in the same order as they appear on the summary sheet(s). To facilitate identification, the documents should be numbered, starting with 1, 2, 3, etc., for each new Disbursement Request, and this number should be clearly marked on the document itself. The total number of items for the total of all summary sheets is noted on the Disbursement Request form.

[8] Description of item. Please describe each item, e.g. "invoice", "receipt", "engineer's certificate", "translation of [...]", etc.

[9] Contract order number and date. It is recommended that the contract is given an original number when it is drawn up between the Recipient and the Contractor. The EBRD will adopt this number for its own record keeping. If the contract has not been given an original number, the EBRD will allocate it a number and advise the Recipient at the time of approval. If the Recipient does not know the number at the time of completing the summary sheet, this part can be left for the EBRD to complete.

The date of the contract/purchase order should also be given in this column.

Note: the same contract may appear in more than one Disbursement Request, if delivery of the goods, works or services (see [11]), and therefore payment for these goods, etc., is made in stages.

[10] Name and address of Contractor. Name and address of Recipient’s counterparty (Contractor) in the contract/purchase order as described in [9].

[11] Brief description of goods, works or services. These goods, works or services should correspond to the details provided in the Contract or other documents presented, and should fall within the Grant Financed Item indicated in [6].

[12] Currency and total amount of Contract. Total amount, in original currency, of the Contract listed in [9].

[13] Currency and amount of eligible expenditure. Per expenditure: total amount due or paid, in original currency, as covered by the invoices or other documents listed in [7] and [8]. When there is more than one "item" for each expenditure, (e.g. an invoice, certificate and receipt, all for the same expenditure), those items should be bracketed and only one amount should be shown in this column.

[14] Amount of financing. For each amount listed in column [13], there should be a corresponding amount in this column [14], calculated at the percentage stated in [6], corresponding to the category of this summary sheet. The amount of financing should be in the original currency of the contract and expenditure (columns 12 and 13). This may or may not be the same as the loan currency or the payment currency.

[15] Total. The amounts of financing, as listed in [14], should be added up into one total amount per currency. For direct Disbursement Requests, amount(s) given here should correspond with the amount(s) given in [9] of the direct Disbursement Request form.

[16] Signature. The request summary sheet should be signed off by or on behalf of the Recipient. See request for Disbursement form for signature requirements.

EXHIBIT 2 – FORM OF LETTER DESIGNATING AUTHORISED SIGNATORIES

[To Be Typed on Letterhead of the Recipient]

[Date]

European Bank for Reconstruction and Development

One Exchange Square

London EC2A 2JN

United Kingdom

Attention: Operation Administration Unit

Subject: Operation No. # (Grant Component)

Letter Designating Authorised Signatories[1]7

Dear Sir/Madam,

With reference to the grant agreement dated ______ (the "Grant Agreement") among the Republic of Moldova, Calea Ferata din Moldova and the European Bank for Reconstruction and Development (the “Bank”), please be advised that any one of the persons whose authenticated specimen signatures appear below, is authorised on behalf of the Recipient to sign Disbursement Requests and any other notices or document required or permitted to be executed under the above mentioned Grant Agreement.

NAME POSITION SPECIMEN SIGNATURE

_______________ _______________ _________________________

_______________ _______________ _________________________

_______________ _______________ _________________________

_______________ _______________ _________________________

All previous notices providing signatures of officials authorised to sign on behalf of the Recipient under the above Grant Agreement are hereby revoked.

Yours faithfully,

For and on Behalf of:

[NAME OF RECIPIENT]

By: ______________________________

Name:

Title:

Notes for completion of the letter designating authorised signatories

• The above authorisation letter is to be signed on behalf of the Recipient by its respective Authorised Representatives. [Please note that, in respect of any action required or permitted to be taken and any documents required or permitted to be executed under this Agreement, the above authorisation letter is to be signed on behalf of the Recipient by the Recipient’s Authorised Signatory as set out in Section 8.02.]

• In the event that each document is to be signed by more than one official, the authorisation letter must state this clearly, and the first sentence must be adjusted accordingly.

  1. 7 Designation may be changed by the Recipient at any time by providing a new Letter Designated Authorised Signatories to the Bank. ↑