I. | F/P : | F/P 1756 (2011) |
| Borrower: | Republic of Moldova |
| Approval by the Administrative Council: | 17 November 2011 |
| Amount approved: | EUR 13 400 000 |
| | | |
II. | Intervention area(s): | Partial financing of eligible investment project for providing access to housing to low-income and vulnerable families throughout Moldova. |
| Planned works and Final Beneficiaries: | The objective of the proposed project is to improve and increase the stock of rental housing to benefit families from socially-vulnerable segments of the population of Moldova. In accordance with state legislation, the Project aims to complete some 15 unfinished apartment blocks in selected municipalities, deliver some 700 social dwellings to accommodate some 2,500 persons from poor and vulnerable families currently unable to access to satisfactory housing conditions. The Final Beneficiaries will be selected locally by an ad hoc commission according to a scoring system, elaborated in accordance with CEB criteria. Selection criteria include housing, employment, family, health and education. People targeted by this component are in the category of the official minimum subsistence level (85€/month).
|
| Location: | 12 municipalities throughout Moldova |
| Estimated total cost of the Project: | Approximately EUR 20.4 million (net of VAT) |
| Indicative cost breakdown: | Cost Description | Local authorities participation (total) (in-kind + works) (EUR) | CEB participation (EUR) | Total cost per objective (EUR) | 1 | 2 | 3 | 4 | Works (incl. in kind) | 6 955 267 | 12 984 600 | 19 939 867 | PIU | | 415 400 | 415 400 | TOTAL | 6 955 267 | 13 400 000 | 20 355 267 | | | | |
|
|
| Financing plan: (in EUR million) | CEB EUR 13.4M (65%) Local authorities & direct investment EUR 7.0M (35%) TOTAL EUR 20.4 M (100%) |
| Progress of works at the time of Loan application: | 0% at the date of FLA signature |
| Schedule of works: | 2012-2018 |
| Anticipated Project Completion Date: | 3 June 2018 |
| Closing Date: | 31 December 2018 |
| Specific conditions: | As a condition precedent for entering into the Disbursement Agreement for the first Tranche, the Borrower shall send to CEB’s satisfaction information or evidence of the following: - A PIU is fully operational and adequately staffed with:
- PIU Director with relevant experience in managing international projects
- Finance Specialist with relevant experience from international project
- Procurement Specialist with relevant experience from international projects;
- Civil Engineer(s) with relevant experience from international projects in similar infrastructure investments;
- All Collaboration Agreement Contracts between each participating municipality/region and the Ministry of Regional Development and Construction are signed and copies sent to CEB;
- All Onlending Contracts between each participating municipality/region and the Ministry of Finance are signed and copies sent to CEB;
- Updated estimates of the Project cost and a financing plan;
- Procurement Plan for the first 12 months;
- Tables with technical indicators and initial situation in each of the participating municipalities.
|
| | | |
III. | Criteria of eligibility: (by intervention area) | The Borrower will comply with the eligibility criteria set out in the Loan Policy under the relevant sector of action. [Project is eligible under the sector of action “Strengthening Social Integration,” line of action “1.2 Housing for low-income persons”.] |